Coronado is looking beautiful this spring! It’s exciting to see the community grow!

This month, our construction teams have been working on thirteen Coronado homes: Homes 1.1, 2.1, 2.5, 3.2, 4.6, 5.4, 5.5, 6.2, 6.5, 7.3, 7.4, and 7.5 and 7.6. Homes 7.2 and 5.7 are next homes on which we will begin construction.

The infrastructure projects (such as the communications and electricity) maintain a level of advancement of 22%, but the urbanization projects (roads, and slope conformation, gardens and retaining walls) have progressed to a level of advancement of more than 84%.