Residences Blog
10/27/2017 We are pleased to announce that the community continues to grow, and progress continues on the construction of the residences and condominiums. During the month, construction began on Houses: 27, 70 and 77, and work continued on Houses: 50, 51, 55, 65, 79, 84 and 85. Houses 44 and 75 are next in line to be delivered, and we will begin the construction on the following residences soon: 39, 18 and 82. Renovations continue for the delivery of the condominiums: 1102 and 1203. In Tower 4, works continue in condominiums: 4101, 4102, 4104, 4106, 4503, 4601, 4605 and 4606. As for Tower 5, we are working on interiors, bathrooms and facades. In Tower 6, masonry work is being carried out on the third level. Work on the infrastructure and urbanization around buildings 4, 5 and 6 is progressing. Click the arrows above to scroll through the gallery.Copala Residences: October Update